The initial focus was on the removal of the WDPF controllers
and the installation of the new Ovation controllers.
All 27 Ovation controllers, 11 workstations
and 6 data-link servers were installed, loaded and
operational by Sunday afternoon.
|
Thorough Planning and Execution
are Key
Up-front planning was crucial to
the successful migration. Emerson worked closely
with the Midland operations group to support the
plant restart plan. The following outline illustrates
the phases of the Midland migration:
Phase 1 - Review existing
logic and graphic code and document custom applications.
Review
operational philosophies with Midland Cogeneration
to ensure that all parties agreed on the approach to
hardware/software replacement and re-deployment.
Phase 2 - Verify hardware
configuration and operational philosophies.
Phase 3 - Migrate
existing logic, database and tuning parameters.
This was an interactive process in which the customer
sent the existing logic to Emerson for initial translation.
The migration approach used by Emerson engineers flagged
potential issues within the existing code. Emerson
then sent suggestions to Midland for implementation
on the existing system, to ensure the existing code
was ready for migration.
Phase 4 - Develop plan for onsite migration.
The Midland plan was dynamic, due to a shortened
project schedule. Initial discussion centered on migration
of all 27 controllers. The outage schedule was shortened
from 5 days to less than 2 days and contingency plans
were developed.
Phase 5 - Factory testing.
Scott
Woodby, senior staff engineer for Midland, visited
Emerson’s Pittsburgh headquarters to
review and test the converted logic and graphics on
the actual field kits that would be installed. Following
the factory test, the focus for installation became
a complete migration of all 27 controllers, all logic,
and all graphics during the short outage. Issues discovered
during the factory testing were either corrected immediately
or integrated while the system was in transit.
Phase 6 - On-site installation.
Emerson assembled a team of experts whose experience
included hardware installation, control logic, graphics,
database and other disciplines. The team was sent to
Midland to execute the migration plan.
The initial focus was on the removal of the WDPF
controllers and the installation of the new Ovation
controllers. Teams of two to three people were assigned
to specific areas of the plant to complete the hardware
installation as quickly and accurately as possible.
Once the initial controllers were installed, some of
the installation teams were re-deployed to begin loading
and inspecting the new equipment. All 27 Ovation controllers,
11 workstations and 6 data-link servers were installed,
loaded and operational by Sunday afternoon.
|