|
It's the mission control center. A semicircular counter
lined with keyboards, monitors and telephones sits in front
of a wall of four 72-inch projection displays. Is it the
Starship Enterprise? NASA headquarters? The Monday Night
Football control room?
Actually, this control center monitors processing of 180
million gallons of wastewater everyday. It's the city of
San Diego's Clean Water Operations Management Network (COMNET) – one
of the world's largest integrated control and information
systems linking wastewater facilities.
COMNET uses process control technology from Emerson Process
Management to coordinate operations at more than 200 locations
over 450 sq. miles, including Point Loma Wastewater Treatment
Plant, North City Water Reclamation Plant, the Metro Biosolids
Center numerous pump stations in the San Diego area, and
South Bay, a fourth water reclamation plant.
A Clean Water Revolution
More than ten years ago, San
Diego's Metropolitan Wastewater Department (MWWD) embarked
on a massive expansion and modernization of its regional wastewater
and water reclamation facilities – an
effort that would become the largest clean water initiative
in the nation. When the project began, San Diego's only treatment
plant was manually operated. To serve the community properly,
the city had to upgrade that plant, and add three new plants
to expand capacity.
To control this expanding wastewater treatment system, San
Diego worked with their Program Manager and Emerson Process
Management to develop COMNET, a management system integrating
all automation, monitoring and information systems for its
entire wastewater process. The system was designed to do
more than just control a new four-plant structure during
and after the expansion – it also improved efficiency and
reduced overall costs.
Jim Mueller, senior civil engineer for the San Diego Metropolitan
Wastewater Department, for one, is proud of the accomplishment.
“We managed to upgrade a modern wastewater facility that
provides our residents with a safe and effective sewer system
that is friendly to the environment, fits in well with the
local community, and incorporates state-of-the-art technology,” he
said.
Safdar Khwaja, Water/Wastewater projects director for Emerson
Process Management on the San Diego COMNET Program agrees. “These
plants are pieces of art,” he said.
In the Beginning
San Diego and Emerson began
the project by installing the WDPF Ò distributed control
system (DCS) at the city's Point Loma plant in the early
1990s, and then in the North City Wastewater Reclamation
Plant and Metro Biosolids Center (MBC) as they were constructed.
WDPF also controlled the associated pump stations.
By 1997, when the city was ready to design and construct
the South Bay Water Reclamation Plant and modernize several
pump stations, Emerson had developed the Ovation Ò Information & Control
system through advances in computer and networking technology.
Ovation, the first DCS to offer real-time, mission-critical
control on a PC platform, provides an unprecedented level
of performance and power. The system's open architecture
reduces the risk of obsolescence often associated with proprietary
control systems and is easily incorporated into existing
IT strategies, providing better and more accessible facility
operation information.
San Diego chose this system to continue its clean water
project, which allowed for integration of SCADA (Supervisory
Control and Data Acquisition) technology, which will monitor
and control more than 100 smaller pumping plants and valve
stations using spread-spectrum radio communication through
the Ovation base.
Four Plants, Numerous Pump Stations, One Control Center
While each facility in San Diego's system also has a local
control room, the COMNET central station is in full control
of points throughout the city's wastewater treatment system,
most importantly the four primary plants.
The COMNET central control station has two operations consoles
with five computer workstations and printers, telephone and
radio communications and access to closed-circuit television
at each of the four primary wastewater facilities. Four 72-inch
projection displays on the wall allow for additional monitoring.
Information is displayed in real time – continuously updated
every second, with realistic 3-D graphical representations
of the treatment process at each facility. Closed-circuit
TV images from each plant are viewed through a moveable window
on the process displays, eliminating the need for TV monitors.
The 24-hour-staffed central station provides full remote
control of each facility without a local operator.
“The system has 45-miles of fiber running through the city.
Each facility can be controlled from five to 20 miles away,” Khwaja
said.
Different Plants, Different Process Challenges
Although each of the four primary San Diego wastewater facilities
can be controlled centrally through COMNET, automating each
plant individually posed a new challenge for Emerson Process
Management engineers.
In 1990, the Point Loma Wastewater Treatment Plant (PLWTP),
was San Diego's only wastewater facility. Expanding the plant,
which included a complete retrofit of all equipment, the
construction of two new digesters and an upgrade of the cogeneration
facility that powers the facility's operation.
According to Khwaja, installing a control system in an existing
large manually operated facility like Point Loma, while another
construction crew was attempting to expand the plant, was
the single most challenging piece of the San Diego COMNET
Program.
“Point Loma was the most arduous because it had to be heavily
modified to install components of the control system like
I/O and sensors,” Khwaja said. “It became quite a surgical
undertaking with technical, logistical and operational challenges.”
While it may have been easier to install process control
components in the North City, MBC and South Bay facilities
as they were constructed, MBC presented its own set of challenges
for engineers, because it involved a complex sludge process.
Almost one-half mile long, with 222,000 square feet of floor
space, the massive MBC facility processes raw and digested
solids to produce biosolids. The plant, with 222,000 square
feet of floor space, contains 231 pumps, over 1,500 motorized
valves and more than 2,000 instruments – all requiring over
16,000 input/output points in the control system.
“It is a very complex system,” Khwaja said. “Designing a
process control system for that facility was like trying
to design retrofit controls for an airplane as big as a 747.”
The work – and challenges – are not complete yet.
The North City plant, which was finished in 1997 with a
WDPF system, is already undergoing an expansion, to be completed
by the end of 2003. Emerson Process Management will migrate
North City to Ovation as part of the expansion. The upgrade,
which can be accomplished more quickly with new engineering
tools developed by Emerson for the power generation market,
will allow operators the flexibility and maintenance ease
of PC-based control, and provide the city with freedom from
component obsolescence issues that eventually surface from
the use of proprietary systems like WDPF.
Advantages of Central Control and Automation
Advances
in process control and the support and services provided by
Emerson Process Management have offered San Diego a variety
of advantages.
Before the Clean Water Program was initiated, San Diego
had only the Point Loma facility, manually operated with
a workforce of 250 people. Despite that plant's expansion
and the addition of three facilities and various pump stations
to the overall network, only 65 additional employees have
been needed for the entire system.
“If these new facilities were operated as the Point Loma
facility used to be operated, we would need more than 600
employees to operate everything,” Mueller said. “Instead,
we now have 315 total employees, and we avoided layoffs by
retraining the previous employees to work in the new environment.”
Employees have been shifted from functions such as pump
and valve monitoring, meter reading and the performance of
various repetitive tasks. In addition, operations and management
reports are now generated automatically.
Savings are also being realized by better control over the
amounts of chemicals used in the normal sewage treatment
process. Ovation constantly adjusts chemical deployment based
on flow levels to optimize usage.
“In the past, in order to have the right amount of chemicals
on hand for fluctuating flows, we had to overcompensate and
often overused chemicals in the treatment process,” Mueller
said. “Now, process control allows the Point Loma plant to
flow-pace its chemicals. There is pinpoint accuracy in the
chemical releasing process, which allows us to avoid wasting
chemicals and results in big savings.”
Another advantage of Ovation is increased energy efficiency.
The energy usage of all equipment, like large pumps, is constantly
monitored and controlled to operate within the most efficient
range.
“A Value Engineering Study done in 1996 showed that we will
realize a cost savings of more than $100 million over 20
years because of central automation and control,” Mueller
said.
Recognized As a Leader
Serving nearly two million customers in the San Diego regional
area, the San Diego Metropolitan Wastewater Department is
meeting increased wastewater system capacity demands while
building facilities that have been nationally recognized
with several awards. The city received the National Wastewater
Management Excellence Award from the Environmental Protection
Agency, the Gold Award from the Association of Metropolitan
Sewerage Agencies and the 1999 Engineering Award form the
California Water Environment Association. |